Tertiary Treatment Requirements

The discharge limits and removal efficiencies your plant must achieve — in plain terms.

Under the EU Urban Wastewater Directive (2024/3019), tertiary treatment must bring total nitrogen down to 10 mg/L (or achieve at least 80% removal) and total phosphorus to 1.0 mg/L for plants between 10,000 and 150,000 PE, or 0.5 mg/L for plants above 150,000 PE. Suspended solids are typically polished to around 10 mg/L. Compliance is judged on annual load-weighted averages rather than single samples, which shapes how a plant is designed and operated.

Discharge Limits at a Glance

0
mg/L
Total Nitrogen (or ≥80% removal)
0.0
mg/L
Total Phosphorus (10k–150k PE)
0.0
mg/L
Total Phosphorus (>150k PE)
0
mg/L
Typical TSS polishing target

What the Numbers Mean for Design

Meeting these limits reliably — not just on a good day, but as an annual average — drives several engineering decisions:

  • Nitrogen: reaching 10 mg/L total nitrogen usually depends on stable nitrification and denitrification, sometimes supported by an additional polishing step.
  • Phosphorus: low phosphorus targets almost always require chemical precipitation combined with effective solids separation, since much of the residual phosphorus is particle-bound.
  • Suspended solids: a final filtration stage protects the phosphorus result and stabilises effluent quality during load peaks.
  • Margins: because compliance is averaged over the year, designs need headroom for storm flows, temperature swings and maintenance downtime.

Engineering Insight: The Phosphorus–Solids Link

Hitting a 0.5 mg/L phosphorus target is as much a solids-removal challenge as a chemical-dosing one. A large share of residual phosphorus leaves the plant attached to fine particles — which is why a reliable final filtration stage is often the decisive factor for the largest plants.

Translating Limits into a Plan

The gap between your current effluent quality and these targets defines the retrofit scope. A structured assessment of your current performance and target values is the fastest way to size that gap and identify the most cost-effective route to compliance.

Figures are EU baseline values

The limits shown reflect the EU-level directive. National transposition may set stricter values or additional parameters, and site-specific permits govern each plant. Use these figures for orientation, and confirm the binding requirements for your location with the competent authority.
Source: Directive (EU) 2024/3019

Ready to upgrade your treatment plant?

Get a preliminary engineering assessment tailored to your plant’s specific conditions and requirements.

Assess Your Plant